US data center moratoriumsUpdated Nov. 18, 2026

Read the report Full screen →

Scroll the page as usual; hold ctrl or ⌘ while scrolling (two fingers on a phone) to zoom the map. Click a county or town for dates, the vote, the ordinance text and its source. The map shows the 1,390 instruments with a location; the other 25 are statewide or unplaced and listed on the state pages.

Read the report

Entitlement risk & power constraints · Updated Nov. 18, 2026

Temporary in name only: 1,073 US data center moratoriums are on record as in force, and 76% of those resolved at their sunset date were extended

Across 46 states, 1,073 municipal and state data center moratoriums or zoning bans are on record as in force, including 163 confirmed by a government record, an official notice or two independent news outlets. Together, these pauses encapsulate 98 planned data center campuses that have yet to break ground, with 15,373 MW of disclosed capacity across the 14 projects with public load figures.

By Jeff AxelrodMoraine Research

  1. 1 · National footprint 1,073 moratoriums on record as in force, across 46 states

    Underwriting takeawayEntitlement risk is no longer confined to Northern Virginia. Search any county or municipality in the register for the ordinance language and procedural scope, where on file.

  2. 2 · Rollover duration risk 56 of 74 pauses past their sunset date with a recorded outcome were extended (76%)

    Underwriting takeawayNever model a statutory sunset date as a site’s reopening date. Treat the stated expiration as the earliest date a jurisdiction might revisit the pause.

  3. 3 · Pipeline exposure 98 pre-construction campuses inside pauses on record as in force

    Underwriting takeawayMoratoriums halt new land-use applications and discretionary permits; projects with vertical construction underway generally retain vested rights.

  4. 4 · The shadow bottleneck 1,900–6,919 MW of requested power under utility large-load actions, without Pennsylvania

    Underwriting takeawayUtility interconnection pauses, collateral mandates and large-load tariffs reach roughly as much pipeline power as every local zoning moratorium combined, even before Pennsylvania’s pending framework takes effect.

Strategic implications by capital role

For developers & site acquirers

Underwrite any municipal pause in a target jurisdiction to extend beyond its initial sunset date: 56 of the 74 moratoriums that reached their scheduled expiration with a recorded outcome were rolled over. More importantly, audit the underlying legal instrument for its exact procedural trigger. Loudoun County’s pause, for example, applies only to applications that need a legislative Board of Supervisors decision.

For debt & equity underwriting

Never hard-code a moratorium’s stated sunset date as the entitlement restart date in a development DCF. Treat the statutory expiration as the earliest possible catalyst window, not a baseline schedule. Currently, 98 pre-construction data center projects sit inside local pauses on record as in force, and the 14 campuses disclosing load figures total 15,373 MW (detailed in Section 3).

For infrastructure platforms & allocators

Municipal zoning freezes are only half the constraint. Utility large-load tariffs, collateral requirements and interconnection pauses, adopted or pending, already reach 1,900–6,919 MW of requested pipeline capacity, matching the megawatt reach of all local zoning pauses combined. If Pennsylvania’s pending large-load guidance is adopted as drafted, the utility figure would be more than double the local one.

1 · Geographic distribution

1,073 pauses on record as in force, 96% of dated ones enacted in 2026

As of Nov. 18, 2026, Moraine tracks 1,073 local and state data center moratoriums and bans on record as in force across 46 states, 163 of them confirmed by a government record, an official notice or two independent news outlets. Of the 970 with an exact adoption date on record, 933 (96%) were adopted in 2026.As of Nov. 18, 2026; n = 1,073 on record as in force; 163 double-coded and confirmed. Moraine Research, https://morainecre.com/resources/research/data-center-moratoria

Activity is heavily concentrated in the Midwest and Southeast, led by Ohio (161 instruments), Michigan (125) and North Carolina (66). On the interactive map, dark red jurisdictions have a pause in force on a government record or in the press; light red ones are tracker leads awaiting primary-source confirmation; and yellow ones have a pending ordinance or a scheduled council vote. Towns and townships are drawn as circles scaled to land area.

Exhibit 1 In-force data center moratoriums by quarter of enactment TakeawayEnactment accelerated sharply in 2026, with 391 in-force pauses adopted in Q3 2026 alone, against 37 adopted before 2026.
  1. Q1 2025 and earlier +5

    5 total

  2. Q2 2025 +3

    8 total

  3. Q3 2025 +8

    16 total

  4. Q4 2025 +21

    37 total

  5. Q1 2026 +128

    165 total

  6. Q2 2026 +336

    501 total

  7. Q3 2026 +391

    892 total

  8. Q4 2026 (to date) +78

    970 total

Adopted that quarter Adopted earlier

Moraine register, Nov. 18, 2026. In-force instruments with a day-precise adoption date (n = 970 of 1,073); enactments before 2025 are combined in the first panel. Pauses that ended before publication aren’t drawn, which underweights earlier cohorts.

View data table
QuarterAdopted that quarterTotal by quarter end
Q1 2025 and earlier55
Q2 202538
Q3 2025816
Q4 20252137
Q1 2026128165
Q2 2026336501
Q3 2026391892
Q4 2026 (to date)78970

2 · Duration & extension risk

Why set dates rarely hold

When a “temporary” 180-day or 365-day study pause reaches its statutory expiration, municipalities mostly extend it rather than reopen the entitlement window. Among the 74 US data center moratoriums whose scheduled sunset date had passed by Nov. 5, 2026 with a documented outcome, 56 (75.7%) were formally extended. Only 18 ended or were replaced by permanent zoning rules, and another 24 passed their stated sunset dates with no recorded action.As of Nov. 18, 2026; n = 74 expired instruments with a documented outcome. Moraine Research, https://morainecre.com/resources/research/data-center-moratoria

In the timeline below, each bar tracks one moratorium from enactment to its initial sunset date. Dashed extensions mark jurisdictions that extended past the initial deadline. The 24 hatched bars are ordinances whose sunset dates passed without a documented vote or press record; some of them likely lapsed quietly without coverage.

For acquisitions and credit teams underwriting land inside a paused jurisdiction: do not model the ordinance sunset date as the entitlement clearing date. Underwrite it as a legislative review milestone.

Exhibit 2 Legislative outcomes for all 98 moratoriums past their initial sunset date Takeaway56 were formally extended and remain on record as in force; 18 expired or were replaced by permanent zoning rules; 24 have no record after their sunset date.
2025 July 2026 July Today 56 Extended, still in force 8 Replaced by permanent rules 10 Ended on schedule 24 End date passed, no outcome on record

Moraine register, Nov. 18, 2026. Enacted instruments with day-precise adoption and expiration dates; proposals never adopted are excluded, and 278 more in-force instruments have sunset dates still ahead. The 18 concluded pauses are 10 that ended (1 lifted early) and 8 replaced by permanent zoning rules. Pauses enacted before 2025 start at the left edge, marked with an arrow.

View data table
InstrumentEnactedSet to endOutcome
Norton city, OHDec. 1, 2025Aug. 28, 2026No outcome on record
Caledonia township, MIFeb. 4, 2026Oct. 17, 2026No outcome on record
Saugatuck township, MIFeb. 11, 2026Oct. 31, 2026No outcome on record
Cascade charter township, MIFeb. 25, 2026Sept. 17, 2026No outcome on record
Mercer County, NDMarch 3, 2026Aug. 5, 2026No outcome on record
Waterford charter township, MIMarch 23, 2026Oct. 1, 2026No outcome on record
Wixom city, MIMarch 24, 2026Sept. 6, 2026No outcome on record
Stephens County, GAApril 14, 2026Oct. 14, 2026No outcome on record
Prairie township, OHApril 15, 2026Oct. 15, 2026No outcome on record
Washington township, OHApril 20, 2026Sept. 5, 2026No outcome on record
Waynesville village, OHMay 4, 2026Oct. 31, 2026No outcome on record
Camden County, GAMay 5, 2026Nov. 1, 2026No outcome on record
Floyd County, GAJune 9, 2026Aug. 28, 2026No outcome on record
Mount Airy city, NCJuly 16, 2026Sept. 14, 2026No outcome on record
Lowndes County, GAAug. 25, 2026Oct. 24, 2026No outcome on record
Escondido city, CAAug. 26, 2026Oct. 10, 2026No outcome on record
Eureka city, CASept. 1, 2026Oct. 16, 2026No outcome on record
Groton town, CTJune 15, 2022June 15, 2023Expired
Kootenai County, IDMarch 11, 2025Sept. 9, 2025Expired
Oliver County, NDMay 6, 2025Aug. 4, 2025Expired
Clark township, MIJune 24, 2025June 30, 2026Expired
LaGrange city, GASept. 23, 2025March 22, 2026Expired
Griffin city, GAJan. 13, 2026July 12, 2026Expired
Lenox township, MIFeb. 2, 2026June 2, 2026Expired
Murray city, KYJune 11, 2026June 18, 2026Expired
Commerce city, CAAug. 11, 2026Sept. 25, 2026Expired
North Tonawanda city, NYJuly 16, 2024July 16, 2027In force (extended)
Jackson County, IASept. 17, 2024Aug. 4, 2027In force (extended)
DeKalb County, GAJuly 8, 2025March 30, 2027In force (extended)
Freeborn County, MNAug. 19, 2025Aug. 19, 2027In force (extended)
Red Willow County, NESept. 22, 2025Sept. 22, 2027In force (extended)
Johnson County, IANov. 6, 2025Nov. 8, 2026No outcome on record
Springfield township, MIDec. 11, 2025Dec. 10, 2026In force (extended)
Crawford County, GAJan. 6, 2026Oct. 1, 2026No outcome on record
Oneida charter township, MIJan. 13, 2026Jan. 24, 2027In force (extended)
Sylvan township, MIJan. 13, 2026July 14, 2027In force (extended)
Sedgwick County, KSJan. 14, 2026Dec. 25, 2026In force (extended)
Pontiac city, MIJan. 21, 2026Jan. 20, 2027In force (extended)
Williamsburg township, OHJan. 26, 2026Jan. 25, 2027In force (extended)
Larimer County, COJan. 27, 2026Feb. 25, 2027In force (extended)
Baltimore County, MDFeb. 2, 2026Jan. 1, 2027In force (extended)
Genoa township, MIFeb. 2, 2026Feb. 2, 2027In force (extended)
Lodi township, MIFeb. 3, 2026Feb. 16, 2027In force (extended)
Hayes township, MIFeb. 9, 2026Feb. 4, 2027In force (extended)
Pierce township, OHFeb. 11, 2026May 31, 2027In force (extended)
Bulloch County, GAFeb. 17, 2026Dec. 31, 2026In force (extended)
Newton County, GAFeb. 17, 2026Dec. 16, 2026In force (extended)
White Lake charter township, MIFeb. 17, 2026Feb. 12, 2027In force (extended)
Dexter township, MIFeb. 17, 2026Feb. 12, 2027In force (extended)
Vienna township, OHFeb. 17, 2026Oct. 16, 2026No outcome on record
Holly township, MIFeb. 18, 2026Feb. 15, 2027In force (extended)
Elmwood township, MIFeb. 18, 2026June 17, 2027In force (extended)
Meriwether County, GAFeb. 24, 2026Nov. 21, 2026In force (extended)
Kings Mountain city, NCFeb. 24, 2026Aug. 25, 2026No outcome on record
Richfield village, OHMarch 3, 2026March 2, 2027In force (extended)
Baldwin Park city, CAMarch 4, 2026March 4, 2027In force (extended)
Rochester Hills city, MIMarch 9, 2026March 4, 2027In force (extended)
Ottawa city, ILMarch 11, 2026Aug. 25, 2027In force (extended)
Scott County, KYMarch 13, 2026Dec. 31, 2026In force (extended)
East Lansing city, MIMarch 17, 2026March 17, 2027In force (extended)
Archbold village, OHApril 6, 2026April 6, 2027In force (extended)
Ada village, OHApril 7, 2026Sept. 1, 2027In force (extended)
Oakley city, CAApril 14, 2026April 14, 2027In force (extended)
Plainfield village, ILApril 20, 2026April 15, 2027In force (extended)
Weathersfield township, OHApril 30, 2026Oct. 30, 2026No outcome on record
Brandon charter township, MIMay 4, 2026April 29, 2027In force (extended)
Durham city, NCMay 4, 2026July 3, 2026No outcome on record
Merrillville town, INMay 26, 2026May 31, 2027In force (extended)
Colquitt County, GAJune 2, 2026Feb. 28, 2027In force (extended)
Imperial city, CAJune 3, 2026May 30, 2027In force (extended)
Charlotte city, NCJune 8, 2026Nov. 5, 2026No outcome on record
Fayette County, KYJune 9, 2026Oct. 31, 2026No outcome on record
Desert Hot Springs city, CAJune 16, 2026July 31, 2026No outcome on record
Walker County, GAJuly 9, 2026Feb. 2, 2027In force (extended)
Patterson city, CAJuly 16, 2026July 15, 2027In force (extended)
Madison County, GAAug. 3, 2026Feb. 22, 2027In force (extended)
Spokane County, WAAug. 18, 2026June 1, 2027In force (extended)
Hawthorne city, CASept. 8, 2026Sept. 8, 2027In force (extended)
Gilroy city, CASept. 14, 2026Oct. 29, 2026No outcome on record
Richmond city, CASept. 15, 2026Sept. 15, 2028In force (extended)
Indio city, CAOct. 7, 2026Oct. 16, 2027In force (extended)
Lake township, OHOct. 26, 2026April 27, 2027In force (extended)
Springfield city, MOJune 29, 2026Oct. 27, 2026No outcome on record
Chillicothe city, OHAug. 24, 2026Sept. 14, 2026Lifted
Coweta County, GAMay 6, 2025Dec. 17, 2025Replaced by permanent rules
Jerome township, OHSept. 3, 2025May 31, 2026Replaced by permanent rules
Aurora city, ILSept. 25, 2025March 25, 2026Replaced by permanent rules
Clarke County, GADec. 2, 2025June 5, 2026Replaced by permanent rules
Covington city, GAJan. 5, 2026July 4, 2026Replaced by permanent rules
Roswell city, GAJan. 12, 2026April 12, 2026Replaced by permanent rules
Richmond County, GAJune 2, 2026July 21, 2026Replaced by permanent rules
Coachella city, CAJune 4, 2026Sept. 25, 2026Replaced by permanent rules
Troup County, GASept. 16, 2025Dec. 15, 2025No outcome on record
Cincinnati city, OHFeb. 11, 2026May 11, 2026No outcome on record
Birmingham city, ALMarch 3, 2026Aug. 30, 2026No outcome on record
Massillon city, OHApril 6, 2026Aug. 14, 2026No outcome on record
Cleveland city, OHJuly 15, 2026Oct. 20, 2026No outcome on record
Davidson County, TNJuly 21, 2026Nov. 1, 2026No outcome on record

3 · Pipeline exposure

98 pre-construction campuses caught in the freeze

Across the 1,068 local moratoriums on record as in force, 41 contain planned data center projects: 98 projects that have not started construction. 27 have no land-use approval yet, and 71 hold an approval or building permit but have not broken ground. The 14 with public power figures total 15,373 MW, 9,000 MW of it one announced project, Stratos Project Area (MIDA). Counting only land outside city limits under county pauses, it’s 84 projects and 14,014 MW.As of Nov. 18, 2026; n = 98 pre-construction projects. Moraine Research, https://morainecre.com/resources/research/data-center-moratoria

From a land-use law perspective, municipal moratoriums freeze the intake and processing of new discretionary applications; projects with active vertical construction generally retain vested development rights. So the exposure count includes only pre-construction projects (27 without approval; 71 approved or permitted, awaiting groundwork).

Power capacity is publicly disclosed for only 14 of the 98 projects, totaling 15,373 MW (12,576 MW of it from developer announcements). That figure is heavily skewed by Stratos Project Area (MIDA) in Box Elder County, Utah, which accounts for 9,000 MW alone; excluding it, the remaining 13 disclosed projects total 6,373 MW. Five additional campuses hold air-quality permits for backup diesel generators totaling 541 MW. Generator nameplate capacity is not continuous utility load, so those figures stay out of the megawatt total. With 84 projects lacking public load figures, true megawatt exposure is materially higher.

Jurisdictional scope (county-wide vs. unincorporated). The baseline count treats a county moratorium as covering the entire county (98 projects / 15,373 MW). Because county zoning authority typically governs only unincorporated land outside city limits, a strict unincorporated filter narrows the exposure to 84 projects and 14,014 MW. Campuses inside incorporated municipalities within a paused county are marked with a dagger (†) in Exhibit 3.

Notably, Loudoun County, Virginia accounts for 49 of the 98 exposed projects (15 without approval; none with public MW in our register), though its pause applies only to applications that need a legislative Board of Supervisors decision.

Exhibit 3

The 98 pre-construction data center campuses inside local moratoriums on record as in force

ProjectOperatorPauseStageMW (basis)
Stratos Project Area (MIDA) O’Leary Digital Box Elder County, UT Approved or incentive granted 9,000 announced
Stargate Saline Township MI OpenAI / Stargate Saline city, MI Approved or incentive granted 1,383 contracted
Colleton campus — Colleton County, SC Entitlement filed 1,000 announced
QTS Madison site (WI) 900 MW electric service agreement QTS Dane County, WI Utility power requested 900 contracted
Prologis Coweta campus † Prologis Coweta County, GA Approved or incentive granted 900 announced
Chatham campus — Chatham County, NC Approved or incentive granted 750 announced
Atmosphere Data Centers Montgomery campus † Atmosphere Data Centers Montgomery County, MD Entitlement filed 360 announced
TEP special agreement (Energy Supply Agreement) for Beale Infrastructure / Humphrey's Peak Beale Infrastructure (operator not named) Pima County, AZ Utility power requested 286 requested
DC BLOX Rockdale campus DC BLOX Rockdale County, GA Permitted 216 announced
Digital Realty Digital Realty Clayton County, GA Permitted 200 announced
PNK Group WI campus PNK Group Wisconsin Rapids city, WI Entitlement filed 150 requested
Bulloch County campus † — Bulloch County, GA Approved or incentive granted 99 announced
DC Blox Indianapolis Data Center Ind1-a DC BLOX Indianapolis city (balance), IN Permitted 78 requested
Washington campus — Eastport city, ME Entitlement filed 51 announced
Data Center Project — El Segundo city, CA Entitlement filed —
Gilroy Data Center — Gilroy city, CA Entitlement filed —
SVY03A Data Center Campus — Hayward city, CA Entitlement filed —
Data center, Monterey Park — Monterey Park city, CA Entitlement filed —
22990 Indian Creek Drive — Loudoun County, VA Entitlement filed —
Allegro North Campus, Building 2A — Loudoun County, VA Entitlement filed —
Bridgefield Tech Center — Loudoun County, VA Entitlement filed —
Clintmar Data Centers — Loudoun County, VA Entitlement filed —
Cross Mill Center — Loudoun County, VA Entitlement filed —
Data center grading permit (STMP-2019-0009) — Loudoun County, VA Entitlement filed —
Dulles Electric Data Centers — Loudoun County, VA Entitlement filed —
H5 Data Center and LC 11 & 12 Data Centers H5 Data Centers Loudoun County, VA Entitlement filed —
IAD-11 Data Center, Aldie — Loudoun County, VA Entitlement filed —
Mercure Business Park (Lots 4A1A, 4A1B, 19-20, 22) — Loudoun County, VA Entitlement filed —
Ridgetop Center, Manekin Plaza, Thayer Rd, Dulles Design, Horseshoe Dr — Loudoun County, VA Entitlement filed —
Telos Data Center / Ashburn Shallow Bay — Loudoun County, VA Entitlement filed —
Twin Creeks Data Centers, Buildings 1-3 COCHRAN MILL TC 3 LLC Loudoun County, VA Entitlement filed —
Unnamed data center filing, Sterling — Loudoun County, VA Entitlement filed —
Voided 260,000 sf data center site plan, Sterling — Loudoun County, VA Entitlement filed —
Data center, Seattle — Seattle city, WA Entitlement filed —
Teachers Ins & Annuity Assn † — Snohomish County, WA Entitlement filed —
Compass Datacenter - Phx II Campus † Compass Datacenters Pima County, AZ Permitted —
Edgeconnex Phx12 † EdgeConneX Pima County, AZ Permitted —
Microsoft Phx 15 Data Center † Microsoft Pima County, AZ Permitted —
AWS Data Center Gilroy - Sfo069 Amazon (AWS) Gilroy city, CA Permitted —
Hayward Data Center — Hayward city, CA Permitted —
CUBE NA Data Center Company LLC † — San Joaquin County, CA Permitted —
ATL2 Data Center — Newton County, GA Permitted —
Amazon Data Services, Inc. Atl089 Campus † Amazon (AWS) Newton County, GA Permitted —
Chirisa Volo LLC † Chirisa Volo LLC Lake County, IL Approved or incentive granted —
T5@Chicago IV, LP † T5 Data Centers Lake County, IL Approved or incentive granted —
Microsoft Corporation - Yellow Facility Microsoft Howard County, MD Permitted —
Iron Gate Data Centers - Eagan — Eagan city, MN Permitted —
Data center, Minneapolis — Minneapolis city, MN Permitted —
Supercomputer LLC — Minneapolis city, MN Permitted —
Cerner Lee's Summit Data Center † Oracle Jackson County, MO Permitted —
Clt 16 12mw Data Center — Charlotte city, NC Permitted —
Solar Data Center White Horse Ranch — Grant County, NM Permitted —
JP Morgan Chase Data Center Project JP Morgan Chase Bank N.A. Orangetown town, NY Approved or incentive granted —
Orangetown Data Center — Orangetown town, NY Permitted —
Crusoe Energy Systems LLC/Crusoe Cloud Holdings LLC data center (City of Springfield, Clar Crusoe Springfield city, OH Approved or incentive granted —
The Constant Company, LLC data center (City of Springfield, Clark County) The Constant Company, LLC Springfield city, OH Approved or incentive granted —
Cmh051 (0125064021) — Washington township, OH Permitted —
CoreWeave, Inc. (DRT) Digital Realty Hillsboro city, OR Approved or incentive granted —
Hillsboro Dft Or1 Data Center — Hillsboro city, OR Permitted —
Iws Anderson Data Center Project Phase 2 — Anderson County, SC Permitted —
Project Mcfly- QTS Clt 1- Phpc QTS York County, SC Permitted —
Cloudburst Data Centers Cloudburst Hays County, TX Permitted —
23751 Overland Drive — Loudoun County, VA Approved or incentive granted —
44150 Wade Drive and 45865 Maries Road rezonings — Loudoun County, VA Approved or incentive granted —
Allegro North Campus, Building 2F Yondr Loudoun County, VA Approved or incentive granted —
Ashburn Center North / Ashburn Technology Park S3 — Loudoun County, VA Approved or incentive granted —
Ashburn Village Blvd / Russell Branch data center — Loudoun County, VA Approved or incentive granted —
Blueridge Group, Chantilly — Loudoun County, VA Approved or incentive granted —
Brambleton Business Campus Data Centers — Loudoun County, VA Approved or incentive granted —
Cochran Tech (Cochran Mill Road) — Loudoun County, VA Approved or incentive granted —
Cologix site, 21745 Beaumeade Circle Cologix Loudoun County, VA Approved or incentive granted —
DC Capital Data Centers — Loudoun County, VA Approved or incentive granted —
Data center with 17 emergency generators (STPL-2022-0016) — Loudoun County, VA Approved or incentive granted —
Dulles 28 Centre / Technology Park — Loudoun County, VA Approved or incentive granted —
EdgeCore AS01, Sterling EdgeCore Loudoun County, VA Permitted —
EdgeCore Data Center (Kincora) EdgeCore Loudoun County, VA Permitted —
EdgeCore Dulles, three data center buildings EdgeCore Loudoun County, VA Approved or incentive granted —
Equinix Ashburn East / Zebra East / Belmont Innovation Campus Equinix Loudoun County, VA Approved or incentive granted —
Farkas Property Rezoning — Loudoun County, VA Approved or incentive granted —
Inova Health System site, new data center layout — Loudoun County, VA Approved or incentive granted —
JK Technology Park #1 — Loudoun County, VA Approved or incentive granted —
JK Technology Park #2 and #3 — Loudoun County, VA Approved or incentive granted —
Kincora Project — Loudoun County, VA Approved or incentive granted —
Loudoun permitted/pipeline DC applications (Inova, STPL-2018-0019) — Loudoun County, VA Permitted —
Pacific Corporate Park, 3 data center buildings Digital Realty Loudoun County, VA Approved or incentive granted —
Relocation Drive Data Center — Loudoun County, VA Approved or incentive granted —
Rollins Property, Chantilly — Loudoun County, VA Approved or incentive granted —
Spring Valley Technology Park — Loudoun County, VA Approved or incentive granted —
Sterling Park Data Center — Loudoun County, VA Approved or incentive granted —
Turner Property — Loudoun County, VA Approved or incentive granted —
Tuscarora Crossing, Land Bay 3 and LB1 Ph1 — Loudoun County, VA Approved or incentive granted —
Unnamed data center filing, Chantilly — Loudoun County, VA Approved or incentive granted —
WS-C2 data center, Sterling — Loudoun County, VA Approved or incentive granted —
Wade Drive Data Center — Loudoun County, VA Approved or incentive granted —
West Dulles Data Centers — Loudoun County, VA Approved or incentive granted —
Yondr Tarring Yondr Loudoun County, VA Approved or incentive granted —
Epic Hosting, LLC † Epic Hosting, LLC Dane County, WI Approved or incentive granted —
Degas LLC Beaver Dam † Degas LLC Dodge County, WI Approved or incentive granted —
Moraine register and public campus register, Nov. 18, 2026. “Planned” means a campus with a utility power request, land-use filing, entitlement approval or building permit where vertical construction has not started; projects without approval are in bold. Duplicate name-and-operator filings, withdrawn applications and superseded records are removed. Reported MW follows a strict order: (1) requested utility service, (2) contracted utility service, (3) total facility load, (4) critical IT load and (5) maximum announced capacity. † Inside an incorporated municipality; counted only under the county-wide reading.

Case studies: five municipal instruments examined in detail

  • Loudoun County, Va.

    Holds the largest concentration of exposed pipeline projects in the country (49 campuses), yet its restriction applies only to applications that need a discretionary Board of Supervisors legislative action. The instrument carries no sunset date and stays in effect while the county writes new standards.

    “enact a temporary pause on Board consideration of certain legislative applications for data centers and substations”County statement, Sept. 16, 2026 · Source ↗
  • Jackson County, Mo.

    Contains a pre-construction campus and imposes a 180-day freeze on processing data center land-use applications.

    “Ordinance #6074 implementing a 180-day moratorium on the processing of data center land use applications”County legislative record · Source ↗
  • Coweta County, Ga.

    Illustrates serial rollover risk. After an initial moratorium in May 2025 that was later replaced, the county adopted a second in June 2026, currently scheduled to sunset on Dec. 13, 2026.

    “a one hundred-eighty (180) day moratorium beginning on June 16, 2026, and expiring on December 13, 2026”Board minutes, June 16, 2026 · Source ↗
  • Kings Mountain, N.C.

    Passed an initial 182-day pause on a split council vote, then extended it at expiration, in line with the 76% national extension rate.

    “it was voted 5-2 to adopt Ordinance 26-11 enacting a 182-day moratorium on permitting new data centers”City council minutes · Source ↗
  • Pima County, Ariz.

    Directs county staff not to take in new data center land-use filings through Jan. 20, 2027. The text quoted here is the draft from the board packet; the adopted language may differ.

    “Pima County Development Services staff shall not intake, accept, or process any applications”Draft ordinance, board packet · Source ↗

4 · The utility bottleneck

Large-load tariffs rival local zoning pauses

Excluding Pennsylvania, where statewide guidance is still pending, 18 utility actions, adopted or pending (large-load tariffs, collateral requirements and interconnection pauses), reach 1,900–6,919 MW of requested power at pipeline data center campuses. All in-force local moratoriums combined reach 2,428–2,714 MW of requested service, inside that band. If Pennsylvania’s large-load framework is finalized, the utility figure rises to 6,100–11,869 MW.As of Nov. 18, 2026; n = 20 utility regulatory actions. Moraine Research, https://morainecre.com/resources/research/data-center-moratoria

Investors must distinguish how these two constraints bind. A municipal zoning moratorium is a binary stop on land-use permitting within one political boundary. A utility large-load tariff, minimum-demand ratchet or collateral requirement changes the project economics, balance-sheet commitments and energization timeline for every large data center customer across a utility’s service territory. So the megawatt figures in this section measure regulatory reach, not canceled load. Because service territories and municipal pauses overlap, the low end of each range counts a campus in one utility territory only and the high end counts it in every overlapping territory.

Exhibit 4 Requested utility load (MW) at pipeline campuses: utility regulatory actions vs. local zoning pauses TakeawayEven excluding Pennsylvania, utility large-load actions reach about as much pipeline power demand as all local zoning pauses combined. Adding Pennsylvania puts utility-reached load at more than double the local moratorium footprint.
0 MW 2k 4k 6k 8k 10k 12k Utility actions · 6,100–11,869 MW Utility actions, without Pennsylvania · 1,900–6,919 MW Local pauses in force · 2,428–2,714 MW

The shaded band is the local range, carried down so each utility bar can be read against it.

Moraine register and campus register, Nov. 18, 2026. The shaded band marks the local moratorium MW range against the utility ranges. For this comparison, “pipeline” runs from site control through active construction, withdrawn projects excluded (Section 3 counts only pre-construction sites). Each capacity measure is summed only within its own reporting basis (requested service, contracted load and so on) and never blended across bases.

View data table
BasisUtility (MW)Utility without PALocal in force
Utility service requested6,100–11,8691,900–6,9192,428–2,714
Utility contracted4,960–13,4484,610–13,0983,683–3,683
Critical IT load5,402–12,3385,102–12,0380–0
Backup generator nameplate4,370–8,0124,370–8,0122,059–2,064
Announced by the developer25,168–63,67919,793–57,85413,540–15,658
Pipeline campuses (count)229–496218–482221–254

The 20 utility regulatory actions behind the figures

UtilityStateActionStatusPipeline campusesRequested MW
Pennsylvania electric distribution companies (PPL, PECO, Duquesne, FirstEnergy PA, UGI)PAotherGuidance, no tariff in force144,950
Pennsylvania electric distribution companiesPAotherPending144,950
Virginia Electric & Power Co (Dominion Energy Virginia)VAtariff approvedAdopted2622,200
ERCOT-region utilities (all TSP/DSP) TXotherAdopted1302,131
ERCOT-region utilities (all TSP/DSP)TXinterconnection pauseAdopted1302,131
Ohio Power Co (AEP Ohio)OHtariff approvedAdopted111,300
Ohio Power Co (AEP Ohio)OHinterconnection pauseHistorical111,300
Ohio Power Co (AEP Ohio)OHminimum-take or collateral requirementTracker lead only111,300
Evergy Missouri West / Evergy Metro (MO)MOtariff approvedAdopted8800
Entergy Louisiana and other LPSC-regulated utilitiesLAotherTracker lead only4300
Georgia Power CoGAminimum-take or collateral requirementAdopted53288
Southwestern Public Service Co (Xcel, SPS)TXtariff pendingPending17200
Union Electric Co (Ameren Missouri)MOtariff approvedAdopted5—
Indiana Michigan Power CoINtariff approvedAdopted4—
Florida Power & Light CoFLtariff pendingPending4—
Evergy Kansas Central / Evergy Kansas South / Evergy Metro (KS)KStariff approvedAdopted2—
Duke Energy Florida, LLCFLtariff deniedPending1—
Appalachian Power Co and Virginia electric cooperativesVAtariff pendingPending0—
Consumers Energy CoMItariff approvedAdopted0—
Florida Public Utilities CoFLtariff pendingPending0—

Upcoming catalyst calendar (next 30 days)

Scheduled sunset dates & municipal hearings

Stated sunset dates reflect ordinance text, not a probability of expiration. Given that 76% of pauses resolved at their sunset date were extended, underwriting teams should expect most of these deadlines to roll over. Another 71 instruments reach their stated sunset dates or hearings in the following 60 days.

  1. Putnam County, GA · Stated expiry
    Tracker lead only; not counted in any headline

  2. Meridian charter township, MI · Stated expiry
    News report; single-coded · Source

  3. Humboldt County, CA · Stated expiry
    Double-coded; government record · Source

  4. Niles city, OH · Stated expiry
    Double-coded; government record · Source

  5. Oakland city, CA · Stated expiry
    Double-coded; government record · Source

  6. San Francisco city, CA · Stated expiry
    Double-coded; two or more independent news sources · Source

  7. San Joaquin County, CA · Stated expiry
    Double-coded; not headline-eligible · Source

  8. Meriwether County, GA · Stated expiry
    Tracker lead only; not counted in any headline

  9. Minneapolis city, MN · Stated expiry
    Double-coded; not headline-eligible · Source

  10. Hillsboro city, OR · Stated expiry
    Double-coded; not headline-eligible · Source

  11. Bloomington city, IL · Stated expiry
    Government record; single-coded · Source

  12. Braceville township, OH · Stated expiry
    Tracker lead only; not counted in any headline

  13. El Dorado city, KS · Stated expiry
    News report; single-coded · Source

  14. San Francisco County, CA · Stated expiry
    Double-coded; two or more independent news sources · Source

  15. Skagit County, WA · Stated expiry
    Government record; single-coded · Source

  16. Boulder County, CO · Stated expiry
    Double-coded; official notice · Source

  17. Johnson City city, TN · Stated expiry
    Tracker lead only; not counted in any headline

  18. Hayward city, CA · Stated expiry
    Double-coded; official notice · Source

  19. Box Elder County, UT · Stated expiry
    Double-coded; not headline-eligible · Source

  20. Howland township, OH · Stated expiry
    Tracker lead only; not counted in any headline

  21. Loudon County, TN · Extension hearing: Public hearing on a resolution extending the temporary moratorium
    Double-coded; two or more independent news sources · Source

  22. Springfield township, MI · Stated expiry
    Tracker lead only; not counted in any headline

  23. Coweta County, GA · Stated expiry
    Double-coded; government record · Source

  24. Cumberland County, NC · Stated expiry
    News report; single-coded · Source

  25. Webster County, MO · Stated expiry
    Double-coded; official notice · Source

  26. Harlingen city, TX · Stated expiry
    Double-coded; two or more independent news sources · Source

  27. Newton County, GA · Stated expiry
    Double-coded; not headline-eligible · Source

Recent legislative activity (trailing 30 days)

Status changes

Every status update cites a primary record or press report. Moraine’s pipeline flags municipal docket changes, and each change is reviewed before publication. The register was last updated Nov. 18, 2026.

  1. Sedgwick County, KS: In force → In force (extended)
    Source

  2. Roswell city, GA: In force → Replaced by permanent rules
    Source

  3. Richmond County, GA: In force → Replaced by permanent rules
    Source

  4. Pierce township, OH: In force → In force (extended)
    Source

  5. Oakley city, CA: In force → In force (extended)
    Source

  6. Los Angeles County, CA: In force → Not a restriction
    Source

  7. Larimer County, CO: In force → In force (extended)
    Source

  8. Hazle township, PA: In force → Not a restriction
    Source

  9. Hazle township, PA: In force → Not a restriction
    Source

  10. Groton town, CT: In force → Replaced by permanent rules
    Source

  11. Falls township, PA: In force → Not a restriction
    Source

  12. Coffee County, TN: In force → Status not established
    Source

  13. Coachella city, CA: In force → Replaced by permanent rules
    Source

  14. Asbury Park city, NJ: In force → Not a restriction
    Source

  15. Archbold village, OH: In force → In force (extended)
    Source

Jurisdictional directory

State-by-state instrument ledger

Each state page catalogs every tracked ordinance with its legal status, enactment and sunset dates, source verification tier, the ordinance text where on file, and the pre-construction campuses inside. Counts below: in force / all instruments.

Methodology overview

How the Moraine Register is constructed

Every tracked instrument is geocoded to a US Census jurisdiction and checked against primary ordinance text, adopted council minutes, official municipal notices or local press coverage; a row with none of those stays labeled as a tracker lead. The headline count reflects all 1,073 instruments on record as in force, and every row displays its verification tier alongside the confirmed, double-coded subset (163 instruments). Because municipal docket coverage is fragmented, every count is a floor. Statistical specifications, inter-coder reliability and spatial join rules are on the methodology page.

Investor FAQ

Frequently asked questions

How many data center moratoriums are currently in force across the United States?

As of Nov. 18, 2026, Moraine tracks 1,073 local and state data center moratoriums and bans on record as in force across 46 states, 163 of them confirmed by a government record, an official notice or two independent news outlets. Of the 970 with an exact adoption date on record, 933 (96%) were adopted in 2026. 470 rest on a single source or aren’t yet confirmed, and 440 appear only on tracker lists. Every row is labeled by its source, on the map and in each list.

What constitutes a municipal data center moratorium versus a permanent zoning ban?

A moratorium is a temporary local law that stops a city, county or town from accepting or approving data center applications, usually rezonings, permits or site plans, for a set period while it writes rules. A ban prohibits the use outright and has no end date.

Do data center moratoriums actually expire on their scheduled sunset dates?

Rarely. Among the 74 US data center moratoriums whose scheduled sunset date had passed by Nov. 5, 2026 with a documented outcome, 56 (75.7%) were formally extended. Only 18 ended or were replaced by permanent zoning rules, and another 24 passed their stated sunset dates with no recorded action.

How many planned data center campuses and megawatts sit inside active pauses?

Across the 1,068 local moratoriums on record as in force, 41 contain planned data center projects: 98 projects that have not started construction. 27 have no land-use approval yet, and 71 hold an approval or building permit but have not broken ground. The 14 with public power figures total 15,373 MW, 9,000 MW of it one announced project, Stratos Project Area (MIDA). Counting only land outside city limits under county pauses, it’s 84 projects and 14,014 MW. Projects already under construction or operating are left out, since they generally hold vested rights. A county instrument is counted county-wide, which can include projects inside towns the county doesn’t govern.

Do utility large-load tariffs restrict more data center capacity than local zoning pauses?

About as much, by requested megawatts. Excluding Pennsylvania, where statewide guidance is still pending, 18 utility actions, adopted or pending (large-load tariffs, collateral requirements and interconnection pauses), reach 1,900–6,919 MW of requested power at pipeline data center campuses. All in-force local moratoriums combined reach 2,428–2,714 MW of requested service, inside that band. If Pennsylvania’s large-load framework is finalized, the utility figure rises to 6,100–11,869 MW.

Does a moratorium in one county trigger copycat ordinances in neighboring jurisdictions?

Not that the data can show. Counties bordering a jurisdiction that adopted a data center moratorium in the prior three months had 2.04 times the odds of adopting their own over the next quarter (95% CI 1.69–2.45; 1,085 instruments, 2025–2026). Shuffling adoption dates within each state 200 times still produces an odds ratio of 1.77, so the data can’t separate imitation from shared state politics.

How complete is the Moraine Register, and how is coding accuracy audited?

It is not complete. In a blind search, the register already held 36 of 43 instruments found independently (84%; likely between 70% and 92%), so treat every count as a floor. A random audit of 50 confirmed rows found the cited source supports the recorded status in 49.