Kansas data center moratoriums & entitlement directory

As of Nov. 18, 2026, Kansas has 25 data center moratoriums or bans on record as in force, including 1 double-coded and confirmed by a government record, an official notice or two independent news outlets. 4 more are proposed or scheduled for a council vote, and 1 earlier pause has expired or been replaced by permanent zoning rules; 2 proposals were rejected. Nationally, 76% (56 of 74) of data center moratoriums that reached their initial sunset date with a recorded outcome were extended. Treat every stated expiration date below as the earliest possible catalyst window, never as a guaranteed reopening date.

Updated Nov. 18, 2026Part of the Moraine US Data Center Moratorium Register

in force (4 bans)
25
double-coded and confirmed
1
proposed or vote scheduled
4
in force with a planned project inside
0

Geographic map: in-force and pending Kansas restrictions

  • Dark red: in-force restriction on a government record or in the press.
  • Light red: in-force restriction reported on industry tracker lists, pending primary-source confirmation.
  • Yellow: ordinance formally proposed or scheduled for a council vote.

Hover over any county or municipality for its current legal status; click for enactment and sunset dates, vote tally, ordinance text and source, where on file.

Showing Kansas only. Pick another state in the panel, or open the national tracker. Open the full-screen tracker →

Upcoming catalyst calendar (next 90 days)

  1. El Dorado city · Stated expiry · Source

  2. Sedgwick County · Stated expiry · Source

  3. Lyon County · Stated expiry · Source

Complete Kansas instrument ledger (32 tracked actions)

Sorted by legal status (in force, pending, concluded). Each record displays its verification tier, including 10 in-force rows resting on unconfirmed tracker leads, published so they can be checked in diligence. Legislative status is never inferred: “Not stated” means no primary document or press report we found gives a sunset date.

Data center moratoriums and bans in Kansas
Jurisdiction Type Status Enacted Ends Pipeline campuses inside Source
Shawnee County
What it says
Shawnee County shall not accept or process any new application seeking County land use approval for the establishment, construction, expansion, or operation of a Data Center.From the adopted minutes. Vote: 2-1
Moratorium In force Aug. 13, 2026 Feb. 17, 2027 0 Double-coded; two or more independent news sources Source ↗
Americus city Ban In force Nov. 3, 2026 Not stated 0 Double-coded; not headline-eligible Source ↗
El Dorado city Ban In force Nov. 3, 2026 Not stated 0 Double-coded; not headline-eligible Source ↗
Emporia city Ban In force Nov. 3, 2026 Not stated 0 Double-coded; not headline-eligible Source ↗
Ottawa city Ban In force Nov. 3, 2026 Not stated 0 Double-coded; not headline-eligible Source ↗
Franklin County Moratorium In force Sept. 2, 2026 Dec. 31, 2028 0 Tracker lead only; not counted in any headline
Dickinson County Moratorium In force July 30, 2026 July 30, 2027 0 Tracker lead only; not counted in any headline
Lyon County Moratorium In force July 23, 2026 Jan. 21, 2027 0 News report; single-coded Source ↗
Lawrence city Moratorium In force July 14, 2026 July 14, 2028 0 News report; single-coded Source ↗
Topeka city Moratorium In force July 14, 2026 Not stated 0 News report; single-coded Source ↗
El Dorado city Moratorium In force July 13, 2026 Nov. 30, 2026 0 News report; single-coded Source ↗
Geary County Moratorium In force June 22, 2026 Not stated 0 Tracker lead only; not counted in any headline
Bourbon County Moratorium In force June 15, 2026 Not stated 0 Tracker lead only; not counted in any headline
South Hutchinson city Moratorium In force May 26, 2026 Not stated 0 Tracker lead only; not counted in any headline
Riley County Moratorium In force May 18, 2026 Not stated 0 News report; single-coded Source ↗
Saline County Moratorium In force March 17, 2026 Not stated 0 News report; single-coded Source ↗
Brown County Moratorium In force March 2, 2026 Not stated 0 Tracker lead only; not counted in any headline
Marion County Moratorium In force March 2, 2026 June 1, 2027 0 Tracker lead only; not counted in any headline
Kingman County Moratorium In force Feb. 9, 2026 Not stated 0 Tracker lead only; not counted in any headline
Sedgwick County Moratorium In force (extended) Jan. 14, 2026 Dec. 25, 2026 0 News report; single-coded Source ↗
Harvey County Moratorium In force Jan. 13, 2026 Dec. 31, 2028 0 News report; single-coded Source ↗
McPherson County Moratorium In force Aug. 4, 2025 Not stated 0 Tracker lead only; not counted in any headline
Coffey County Moratorium In force Not stated Not stated 0 News report; single-coded Source ↗
Marysville city Moratorium In force Not stated Not stated 0 Tracker lead only; not counted in any headline
Oakley city Moratorium In force (extended) Not stated Not stated 0 News report; single-coded Source ↗
Neosho County Moratorium Proposed May 19, 2026 June 1, 2027 0 News report; single-coded Source ↗
Gardner city Moratorium Proposed Not stated Not stated 0 News report; single-coded Source ↗
Miami County Moratorium Proposed Not stated Not stated 0 News report; single-coded Source ↗
Tonganoxie city Moratorium Proposed Not stated Not stated 0 News report; single-coded Source ↗
Leavenworth County Moratorium Expired May 13, 2026 Not stated 0 News report; single-coded Source ↗
Edgerton city Moratorium Rejected Not stated Not stated 0 News report; single-coded
Reno County Ban Rejected Not stated Not stated 0 Double-coded; not headline-eligible Source ↗

* The ordinance has a conditional sunset trigger (for example, “remains in effect until permanent industrial zoning standards are adopted”); hover the asterisk for the ordinance text.

Kansas entitlement FAQ

How many active data center moratoriums are currently in force across Kansas?

As of Nov. 18, 2026, Kansas has 25 data center moratoriums or bans on record as in force, including 1 double-coded and confirmed by a government record, an official notice or two independent news outlets. 4 more are proposed or scheduled for a council vote, and 1 earlier pause has expired or been replaced by permanent zoning rules; 2 proposals were rejected. The list may be incomplete; nationally, a blind search found 83.7% of instruments already in the register.

Which planned Kansas data center campuses are affected by local permitting freezes?

None of the in-force instruments in Kansas has a planned data center project inside its boundary on Moraine's map. Projects under construction or operating aren't affected: they already hold their approvals.

For national benchmarks, source-tier definitions and statistical methodology, see the Moraine US Data Center Moratorium Register.