Missouri data center moratoriums & entitlement directory
As of Nov. 18, 2026, Missouri has 24 data center moratoriums or bans on record as in force, including 9 double-coded and confirmed by a government record, an official notice or two independent news outlets. One more instrument is proposed or scheduled for a council vote, and 2 earlier pauses have expired or been replaced by permanent zoning rules. Nationally, 76% (56 of 74) of data center moratoriums that reached their initial sunset date with a recorded outcome were extended. Treat every stated expiration date below as the earliest possible catalyst window, never as a guaranteed reopening date.
- in force (2 bans)
- 24
- double-coded and confirmed
- 9
- proposed or vote scheduled
- 1
- in force with a planned project inside
- 1
Geographic map: in-force and pending Missouri restrictions
- Dark red: in-force restriction on a government record or in the press.
- Light red: in-force restriction reported on industry tracker lists, pending primary-source confirmation.
- Yellow: ordinance formally proposed or scheduled for a council vote.
Hover over any county or municipality for its current legal status; click for enactment and sunset dates, vote tally, ordinance text and source, where on file.
Exposed pipeline: pre-construction campuses inside Missouri pauses
This ledger lists only pre-construction pipeline projects: a documented utility power request, land-use application, entitlement approval or building permit, with vertical construction not started. Operating campuses and sites under construction generally hold vested approvals and are excluded.
- Red text: projects without an initial land-use approval.
- Jurisdictional note: a county instrument lists every planned project inside the county boundary, including sites inside incorporated municipalities that may hold their own zoning authority.
- 1 planned project
Jackson County · 1 planned
Cerner Lee's Summit Data Center (Oracle)
Double-coded; government record
Complete Missouri instrument ledger (29 tracked actions)
Sorted by legal status (in force, pending, concluded). Each record displays its verification tier, including 6 in-force rows resting on unconfirmed tracker leads, published so they can be checked in diligence. Legislative status is never inferred: “Not stated” means no primary document or press report we found gives a sunset date.
| Jurisdiction | Type | Status | Enacted | Ends | Pipeline campuses inside | Source |
|---|---|---|---|---|---|---|
St. Joseph city What it saysAN EMERGENCY ORDINANCE TEMPORARILY SUSPENDING THE ACCEPTANCE AND PROCESSING OF APPLICATIONS RELATING TO THE DEVELOPMENT, CONSTRUCTION, OR EXPANSION OF DATA CENTER FACILITIES WITHIN CITY LIMITS ... add language which places a timeframe on the temporary suspension of not less than one year.From the adopted minutes | Moratorium | In force | July 20, 2026 | July 20, 2027 | 0 | Double-coded; government record Source ↗ |
St. Charles County What it saysAN ORDINANCE ESTABLISHING A TEMPORARY MORATORIUM ON THE APPROVAL, CONSTRUCTION, EXPANSION, OR OPERATION OF CERTAIN LARGE-SCALE DATA CENTERS WITHIN ST. CHARLES COUNTY, MISSOURIFrom the adopted minutes. Vote: 7-0 | Moratorium | In force | July 13, 2026 | Not stated | 0 | Double-coded; government record Source ↗ |
Independence city What it saysA resolution declaring a 180-day moratorium on the processing of applications related to and issuance of city permits or licenses related to the installation or use of data processing and hosting facilities located in the City of Independence, Missouri, for projects or applications not already submitted to, authorized, or approved by the City.From the adopted minutes. Vote: 7-0 | Moratorium | In force | July 6, 2026 | Jan. 2, 2027 | 0 | Double-coded; government record Source ↗ |
Jackson County What it saysOrdinance #6074 implementing a 180-day moratorium on the processing of data center land use applications and Battery Energy Storage System land use applications by Jackson CountyFrom the adopted minutes | Moratorium | In force | June 22, 2026 | Dec. 19, 2026 | 1 | Double-coded; government record Source ↗ |
Webster County What it saysthe Webster County Commission adopted a temporary six-month moratorium relating to certain developments in the unincorporated areas of Webster County, including data centers, solar energy systems, wind energy conversion systems, and battery energy storage systems.From an official notice. Vote: Unanimous | Moratorium | In force | June 16, 2026 | Dec. 15, 2026 | 0 | Double-coded; official notice Source ↗ |
St. Charles city What it saysby defining "Data Center" under the City's Zoning Code (Chapter 400) without specifically listing it in any district the City's Zoning Code, data centers are therefore effectively prohibited as a use in any districtFrom the instrument | Ban | In force | May 19, 2026 | Not stated | 0 | Double-coded; official notice Source ↗ |
Columbia city What it saysThe city council also approved an ordinance that will pause the acceptance and processing of permits for new or expanding data center projects for one year.From a news report. Vote: 6-0 | Moratorium | In force | May 18, 2026 | May 18, 2027 | 0 | Double-coded; two or more independent news sources Source ↗ |
St. Peters city What it saysimposes a moratorium on zoning amendments, site plans, special use permits, and building permits for this use; outlines a waiver process through application to the Board of Adjustment; and sets the moratorium term for up to one year from the ordinance’s effective date.From draft text; the adopted version may differ | Moratorium | In force | May 14, 2026 | Not stated | 0 | Double-coded; government record Source ↗ |
Peculiar city What it saysthe Peculiar Board of Aldermen voted unanimously Monday evening to remove data centers as a permitted use in the I-1 Light Industrial Zoning District.From a news report. Vote: Unanimous | Ban | In force | Not stated | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
| Wentzville city | Moratorium | In force | Oct. 7, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| Cedar County | Moratorium | In force | Sept. 8, 2026 | Sept. 8, 2027 | 0 | News report; single-coded Source ↗ |
| Palmyra city | Moratorium | In force | Sept. 3, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Ralls County | Moratorium | In force | Aug. 24, 2026 | Sept. 1, 2027 | 0 | News report; single-coded Source ↗ |
| Pacific city | Moratorium | In force | Aug. 4, 2026 | Aug. 4, 2027 | 0 | News report; single-coded Source ↗ |
| Oak Grove city | Moratorium | In force | Aug. 3, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Nodaway County | Moratorium | In force | July 21, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Neosho city | Moratorium | In force | July 7, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Ava city | Moratorium | In force | July 1, 2026 | July 1, 2027 | 0 | News report; single-coded Source ↗ |
| Marion County | Moratorium | In force | June 15, 2026 | June 15, 2027 | 0 | News report; single-coded Source ↗ |
| Stone County | Moratorium | In force | June 4, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| St. Peters city | Moratorium | In force | May 14, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Camdenton city | Moratorium | In force | May 5, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| Camdenton city | Moratorium | In force | May 5, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Pettis County | Moratorium | In force | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Franklin County | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Benton County | Moratorium | In litigation | Aug. 10, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Springfield city | Moratorium | In litigation | June 29, 2026 | Oct. 27, 2026 | 0 | News report; single-coded Source ↗ |
| St. Charles city | Moratorium | Replaced by permanent rules | Aug. 22, 2025 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Peculiar city | Moratorium | Replaced by permanent rules | Aug. 19, 2024 | Not stated | 0 | Tracker lead only; not counted in any headline |
* The ordinance has a conditional sunset trigger (for example, “remains in effect until permanent industrial zoning standards are adopted”); hover the asterisk for the ordinance text.
Missouri entitlement FAQ
How many active data center moratoriums are currently in force across Missouri?
As of Nov. 18, 2026, Missouri has 24 data center moratoriums or bans on record as in force, including 9 double-coded and confirmed by a government record, an official notice or two independent news outlets. One more instrument is proposed or scheduled for a council vote, and 2 earlier pauses have expired or been replaced by permanent zoning rules. The list may be incomplete; nationally, a blind search found 83.7% of instruments already in the register.
Which planned Missouri data center campuses are affected by local permitting freezes?
1 of the in-force instruments have at least one planned data center project inside the boundary (county-wide reading). Projects under construction or operating aren't affected: they already hold their approvals. Whether a planned project is covered depends on the approvals it already holds and on the instrument's own scope; the table quotes the text where we have it.
For national benchmarks, source-tier definitions and statistical methodology, see the Moraine US Data Center Moratorium Register.