As of Nov. 18, 2026, Minnesota has 28 data center moratoriums or bans on record as in force, including 3 double-coded and confirmed by a government record, an official notice or two independent news outlets. 7 more are proposed or scheduled for a council vote, and 0 earlier pauses have expired or been replaced by permanent zoning rules. Nationally, 76% (56 of 74) of data center moratoriums that reached their initial sunset date with a recorded outcome were extended. Treat every stated expiration date below as the earliest possible catalyst window, never as a guaranteed reopening date.
- in force
- 28
- double-coded and confirmed
- 3
- proposed or vote scheduled
- 7
- in force with a planned project inside
- 2
Geographic map: in-force and pending Minnesota restrictions
- Dark red: in-force restriction on a government record or in the press.
- Light red: in-force restriction reported on industry tracker lists, pending primary-source confirmation.
- Yellow: ordinance formally proposed or scheduled for a council vote.
Hover over any county or municipality for its current legal status; click for enactment and sunset dates, vote tally, ordinance text and source, where on file.
Exposed pipeline: pre-construction campuses inside Minnesota pauses
This ledger lists only pre-construction pipeline projects: a documented utility power request, land-use application, entitlement approval or building permit, with vertical construction not started. Operating campuses and sites under construction generally hold vested approvals and are excluded.
- Red text: projects without an initial land-use approval.
- Jurisdictional note: a county instrument lists every planned project inside the county boundary, including sites inside incorporated municipalities that may hold their own zoning authority.
- 2 planned projects
Minneapolis city · 2 planned
Data center, Minneapolis, Supercomputer LLC
Double-coded; not headline-eligible - 1 planned project
Eagan city · 1 planned
Iron Gate Data Centers - Eagan
Double-coded; not headline-eligible
Upcoming catalyst calendar (next 90 days)
Minneapolis city · Stated expiry · Source
Complete Minnesota instrument ledger (37 tracked actions)
Sorted by legal status (in force, pending, concluded). Each record displays its verification tier, including 9 in-force rows resting on unconfirmed tracker leads, published so they can be checked in diligence. Legislative status is never inferred: “Not stated” means no primary document or press report we found gives a sunset date.
| Jurisdiction | Type | Status | Enacted | Ends | Pipeline campuses inside | Source |
|---|---|---|---|---|---|---|
Plymouth city * What it says1. Planning or zoning applications related to a data center shall not be accepted or considered while the moratorium is in effect. 2. No proposal for rezoning related to a data center (which includes planned unit development amendments and planned unit development concepts) or comprehensive plan amendment shall be recommended for approval by the Plymouth Planning Commission or be or approved by the City Council.From the instrument | Moratorium | In force | Sept. 8, 2026 | Sept. 8, 2027 | 0 | Double-coded; official notice Source ↗ |
Elk River city What it saysMoved by [name] [name] and seconded by [name] [name] to adopt Ordinance 26-17 establishing a one-year moratorium on the review, approval, and development of data centers in the City of Elk River.From the adopted minutes. Vote: 5-0 | Moratorium | In force | Aug. 3, 2026 | Not stated | 0 | Double-coded; government record Source ↗ |
Freeborn County What it saysTemporary Interim Zoning Ordinance No. 25-244, which instituted a 12-month temporary moratorium on the acceptance, processing, and approval of permits for Data Centers within the unincorporated areas of Freeborn County ... extends the moratorium in Ordinance No. 25-244 for one year, through August 19, 2027, continuing all restrictions in the original ordinance.From draft text; the adopted version may differ | Moratorium | In force (extended) | Aug. 19, 2025 | Aug. 19, 2027 | 0 | Double-coded; official notice Source ↗ |
| Caledonia city | Moratorium | In force | Oct. 26, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Woodbury city | Moratorium | In force | Sept. 23, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| North Mankato city | Moratorium | In force | Sept. 21, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Bemidji city | Moratorium | In force | Sept. 14, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Carlton County | Moratorium | In force | Aug. 24, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Chisago County | Moratorium | In force | Aug. 5, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Minnetrista city | Moratorium | In force | Aug. 3, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Todd County | Moratorium | In force | July 21, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Mankato city | Moratorium | In force | July 13, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Apple Valley city | Moratorium | In force | July 9, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Pine County | Moratorium | In force (extended) | July 7, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Inver Grove Heights city | Moratorium | In force | June 26, 2026 | June 26, 2027 | 0 | News report; single-coded Source ↗ |
| St. Joseph city | Moratorium | In force | June 15, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Le Sueur County | Moratorium | In force | May 26, 2026 | May 26, 2027 | 0 | News report; single-coded Source ↗ |
| Minneapolis city | Moratorium | In force | May 21, 2026 | Nov. 21, 2026 | 2 | Double-coded; not headline-eligible Source ↗ |
| Wright County | Moratorium | In force | May 19, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Elko New Market city | Moratorium | In force | May 14, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Waite Park city | Moratorium | In force | May 4, 2026 | May 4, 2027 | 0 | News report; single-coded Source ↗ |
| Lonsdale city | Moratorium | In force | April 30, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Rosemount city | Moratorium | In force | April 21, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| Carver city | Moratorium | In force | April 6, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Eagan city | Moratorium | In force | Feb. 17, 2026 | Feb. 17, 2027 | 1 | Double-coded; not headline-eligible Source ↗ |
| Cambridge city | Moratorium | In force | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Isanti city | Moratorium | In force | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| North Branch city | Moratorium | In force | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Blue Earth County | Moratorium | Proposed | Aug. 25, 2026 | Not stated | 0 | News report; single-coded |
| Otsego city | Moratorium | Vote scheduled | July 27, 2026 | July 27, 2027 | 0 | News report; single-coded Source ↗ |
| Minnesota | Moratorium | Proposed | Not stated | Not stated | — | News report; single-coded Source ↗ |
| Nicollet County | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Nobles County | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Rice city | Moratorium | Vote scheduled | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Thief River Falls city | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Hastings city | Moratorium | Status not established | Aug. 17, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| Denmark township | Ban | Status not established | Not stated | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
* The ordinance has a conditional sunset trigger (for example, “remains in effect until permanent industrial zoning standards are adopted”); hover the asterisk for the ordinance text.
Minnesota entitlement FAQ
How many active data center moratoriums are currently in force across Minnesota?
As of Nov. 18, 2026, Minnesota has 28 data center moratoriums or bans on record as in force, including 3 double-coded and confirmed by a government record, an official notice or two independent news outlets. 7 more are proposed or scheduled for a council vote, and 0 earlier pauses have expired or been replaced by permanent zoning rules. The list may be incomplete; nationally, a blind search found 83.7% of instruments already in the register.
Which planned Minnesota data center campuses are affected by local permitting freezes?
2 of the in-force instruments have at least one planned data center project inside the boundary (county-wide reading). Projects under construction or operating aren't affected: they already hold their approvals. Whether a planned project is covered depends on the approvals it already holds and on the instrument's own scope; the table quotes the text where we have it.
For national benchmarks, source-tier definitions and statistical methodology, see the Moraine US Data Center Moratorium Register.