Indiana data center moratoriums & entitlement directory
As of Nov. 18, 2026, Indiana has 30 data center moratoriums or bans on record as in force, including 5 double-coded and confirmed by a government record, an official notice or two independent news outlets. 7 more are proposed or scheduled for a council vote, and 2 earlier pauses have expired or been replaced by permanent zoning rules; 1 proposal was rejected. Nationally, 76% (56 of 74) of data center moratoriums that reached their initial sunset date with a recorded outcome were extended. Treat every stated expiration date below as the earliest possible catalyst window, never as a guaranteed reopening date.
- in force (2 bans)
- 30
- double-coded and confirmed
- 5
- proposed or vote scheduled
- 7
- in force with a planned project inside
- 1
Geographic map: in-force and pending Indiana restrictions
- Dark red: in-force restriction on a government record or in the press.
- Light red: in-force restriction reported on industry tracker lists, pending primary-source confirmation.
- Yellow: ordinance formally proposed or scheduled for a council vote.
Hover over any county or municipality for its current legal status; click for enactment and sunset dates, vote tally, ordinance text and source, where on file.
Exposed pipeline: pre-construction campuses inside Indiana pauses
This ledger lists only pre-construction pipeline projects: a documented utility power request, land-use application, entitlement approval or building permit, with vertical construction not started. Operating campuses and sites under construction generally hold vested approvals and are excluded.
- Red text: projects without an initial land-use approval.
- Jurisdictional note: a county instrument lists every planned project inside the county boundary, including sites inside incorporated municipalities that may hold their own zoning authority.
- 1 planned project
Indianapolis city (balance) · 1 planned
DC Blox Indianapolis Data Center Ind1-a (DC BLOX)
Double-coded; two or more independent news sources
Complete Indiana instrument ledger (41 tracked actions)
Sorted by legal status (in force, pending, concluded). Each record displays its verification tier, including 10 in-force rows resting on unconfirmed tracker leads, published so they can be checked in diligence. Legislative status is never inferred: “Not stated” means no primary document or press report we found gives a sunset date.
| Jurisdiction | Type | Status | Enacted | Ends | Pipeline campuses inside | Source |
|---|---|---|---|---|---|---|
Evansville city What it saysThe Evansville City Council approved an ordinance Monday, Oct. 5 evening instituting a 180-day moratorium on data center development within city limits. ... The ordinance states the council believes it’s in the best interests of city residents for data centers be deferred for 180 days so potential impacts can be studied.From a news report | Moratorium | In force | Oct. 5, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Indianapolis city (balance) What it saysThe Metropolitan Development Commission on Wednesday unanimously approved a data center moratorium for Indianapolis through the end of 2027. ... A moratorium acts as a temporary freeze on an action, in this case the development of new data centers.From a news report | Moratorium | In force | Aug. 19, 2026 | Dec. 31, 2027 | 1 | Double-coded; two or more independent news sources Source ↗ |
Cass County What it saysthe three county commissioners voted unanimously to bar the construction of data centers in the countyFrom a news report. Vote: Unanimous | Ban | In force | April 20, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Marshall County What it saysMarshall County Commissioners have approved a landmark measure prohibiting data center development, marking the first lifelong ban on such facilities in Indiana.From a news report | Ban | In force | April 20, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Starke County What it sayswhich will impose a twelve (12) month moratorium on the acceptance, processing, or approval of any building permits, improvement location permits, or site plan applications for Hyperscale Data Center Projects within the unincorporated areas of Starke County, Indiana.From an official notice. Vote: 3-0 | Moratorium | In force | Dec. 15, 2025 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
| Gary city | Moratorium | In force | Sept. 16, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Steuben County | Moratorium | In force | Sept. 15, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Wabash County | Moratorium | In force | Aug. 31, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Clark County | Moratorium | In force | Aug. 27, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| Elkhart city | Moratorium | In force | Aug. 27, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Howard County | Moratorium | In force | Aug. 17, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Charlestown city | Moratorium | In force | Aug. 3, 2026 | Aug. 3, 2027 | 0 | News report; single-coded Source ↗ |
| Jeffersonville city | Moratorium | In force | Aug. 3, 2026 | Aug. 3, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| New Albany city | Moratorium | In force | July 16, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Madison County | Moratorium | In force | June 16, 2026 | June 16, 2027 | 0 | News report; single-coded Source ↗ |
| Boone County | Moratorium | In force | June 15, 2026 | June 15, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| Merrillville town | Moratorium | In force (extended) | May 26, 2026 | May 31, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| Fayette County | Moratorium | In force | May 5, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| DeKalb County | Moratorium | In force | April 13, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Grant County | Moratorium | In force | March 16, 2026 | March 16, 2028 | 0 | Tracker lead only; not counted in any headline |
| Fulton County | Moratorium | In force | March 2, 2026 | March 2, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| Dearborn County | Moratorium | In force | Feb. 24, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Huntington County | Moratorium | In force | Feb. 23, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Shelby County | Moratorium | In force | Feb. 23, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Pulaski County | Moratorium | In force | Jan. 20, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Franklin County | Moratorium | In force | Dec. 24, 2025 | Feb. 24, 2027 | 0 | News report; single-coded Source ↗ |
| Starke County | Moratorium | In force | Dec. 15, 2025 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Putnam County | Moratorium | In force | Nov. 17, 2025 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Owen County | Moratorium | In force | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Porter township | Moratorium | In force | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Warrick County | Moratorium | Vote scheduled | Aug. 11, 2026 | Feb. 7, 2027 | 0 | News report; single-coded Source ↗ |
| Valparaiso city | Moratorium | Vote scheduled | Aug. 10, 2026 | July 31, 2028 | 0 | News report; single-coded Source ↗ |
| Fort Wayne city | Moratorium | Vote scheduled | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Michigan City city | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| South Bend city | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| St. Joseph County | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Washington city | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Miami County | Moratorium | Status not established | May 4, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| White County | Moratorium | Replaced by permanent rules | Oct. 20, 2025 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Marshall County | Moratorium | Replaced by permanent rules | Feb. 3, 2025 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Vermillion County | Moratorium | Rejected | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
* The ordinance has a conditional sunset trigger (for example, “remains in effect until permanent industrial zoning standards are adopted”); hover the asterisk for the ordinance text.
Indiana entitlement FAQ
How many active data center moratoriums are currently in force across Indiana?
As of Nov. 18, 2026, Indiana has 30 data center moratoriums or bans on record as in force, including 5 double-coded and confirmed by a government record, an official notice or two independent news outlets. 7 more are proposed or scheduled for a council vote, and 2 earlier pauses have expired or been replaced by permanent zoning rules; 1 proposal was rejected. The list may be incomplete; nationally, a blind search found 83.7% of instruments already in the register.
Which planned Indiana data center campuses are affected by local permitting freezes?
1 of the in-force instruments have at least one planned data center project inside the boundary (county-wide reading). Projects under construction or operating aren't affected: they already hold their approvals. Whether a planned project is covered depends on the approvals it already holds and on the instrument's own scope; the table quotes the text where we have it.
For national benchmarks, source-tier definitions and statistical methodology, see the Moraine US Data Center Moratorium Register.