North Carolina data center moratoriums & entitlement directory
As of Nov. 18, 2026, North Carolina has 66 data center moratoriums or bans on record as in force, including 10 double-coded and confirmed by a government record, an official notice or two independent news outlets. 7 more are proposed or scheduled for a council vote, and 3 earlier pauses have expired or been replaced by permanent zoning rules; 2 proposals were rejected. Nationally, 76% (56 of 74) of data center moratoriums that reached their initial sunset date with a recorded outcome were extended. Treat every stated expiration date below as the earliest possible catalyst window, never as a guaranteed reopening date.
- in force (1 bans)
- 66
- double-coded and confirmed
- 10
- proposed or vote scheduled
- 7
- in force with a planned project inside
- 2
Geographic map: in-force and pending North Carolina restrictions
- Dark red: in-force restriction on a government record or in the press.
- Light red: in-force restriction reported on industry tracker lists, pending primary-source confirmation.
- Yellow: ordinance formally proposed or scheduled for a council vote.
Hover over any county or municipality for its current legal status; click for enactment and sunset dates, vote tally, ordinance text and source, where on file.
Exposed pipeline: pre-construction campuses inside North Carolina pauses
This ledger lists only pre-construction pipeline projects: a documented utility power request, land-use application, entitlement approval or building permit, with vertical construction not started. Operating campuses and sites under construction generally hold vested approvals and are excluded.
- Red text: projects without an initial land-use approval.
- Jurisdictional note: a county instrument lists every planned project inside the county boundary, including sites inside incorporated municipalities that may hold their own zoning authority.
- 1 planned project
Chatham County · 1 planned
Chatham campus
Double-coded; two or more independent news sources - 1 planned project
Charlotte city · 1 planned
Clt 16 12mw Data Center
Double-coded; not headline-eligible
Complete North Carolina instrument ledger (78 tracked actions)
Sorted by legal status (in force, pending, concluded). Each record displays its verification tier, including 24 in-force rows resting on unconfirmed tracker leads, published so they can be checked in diligence. Legislative status is never inferred: “Not stated” means no primary document or press report we found gives a sunset date.
| Jurisdiction | Type | Status | Enacted | Ends | Pipeline campuses inside | Source |
|---|---|---|---|---|---|---|
Raleigh city What it saysRaleigh will temporarily halt approvals for certain large-scale data centers after the City Council voted 7-1 Tuesday night to impose a six-month moratoriumFrom a news report. Vote: 7-1 | Moratorium | In force | Oct. 6, 2026 | April 6, 2027 | 0 | Double-coded; two or more independent news sources Source ↗ |
Cary town What it saysUnder the moratorium, Cary will temporarily suspend development approvals, rezoning applications, development plans and building permits associated with data centers seeking to locate in the town.From a news report. Vote: Unanimous | Moratorium | In force | Aug. 27, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Durham County * What it saysThe Durham Board of County Commissioners passed a nine-month data center moratorium in a 4-1 vote Monday evening. The measure prohibits accepting, processing and approving development of new data centers in the county, with an exception for some under 100,000 square feet.From a news report. Vote: 4-1 | Moratorium | In force | Aug. 24, 2026 | May 18, 2027 | 0 | Double-coded; official notice Source ↗ |
Jackson County What it saysThis Moratorium shall prohibit the issuance of any permit within the County’s planning and development regulation for data center development including but not limited to zoning, development, building, and demolition permits as well as receiving submittals for soil erosion and sedimentation control plans.From draft text; the adopted version may differ | Moratorium | In force | Aug. 18, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Durham city * What it saysA temporary moratorium is hereby imposed commencing on May 4, 2026 and expiring no later than July 3, 2026, or on approval of new zoning regulations regarding data centers, data processing facilities, cryptocurrency mining, and any other uses associated with data processing facilities not yet defined by the Durham Unified Development Ordinance.From the instrument. Vote: Unanimous | Moratorium | End date passed; no outcome on record | May 4, 2026 | July 3, 2026 | 0 | Double-coded; two or more independent news sources Source ↗ |
Orange County What it saysA temporary moratorium is hereby imposed for a period of one (1) year from the effective date of this Ordinance. During this period, the County shall not accept, process, or approve any applications for the following development approvals: • Special Use Permits; • Conditional Zoning Permits; • Zoning Map Amendments (rezoning requests)From the instrument. Vote: Unanimous | Moratorium | In force | April 21, 2026 | April 21, 2027 | 0 | Double-coded; government record Source ↗ |
Apex town * What it saysINSTITUTING A TEMPORARY MORATORIUM ON THE PERMITTING OF DATA CENTERS, DATA PROCESSING FACILITIES, CRYPTOCURRENCY MINING OPERATIONS AND ANY USE ASSOCIATED WITH DATA PROCESSING FACILITIES WITHIN THE TOWN OF APEX ... A temporary moratorium is hereby imposed commencing on April 28, 2026, and expiring no later than April 27, 2027From the instrument. Vote: Unanimous | Moratorium | In force | April 14, 2026 | April 27, 2027 | 0 | Double-coded; two or more independent news sources Source ↗ |
Kings Mountain city What it saysadopt Ordinance 26-11 enacting a 182-day moratorium on permitting new data centers begin on February 24, 2026From the adopted minutes. Vote: 5-2 | Moratorium | End date passed; no outcome on record | Feb. 24, 2026 | Aug. 25, 2026 | 0 | Double-coded; government record Source ↗ |
Canton town What it saysthe proposed moratorium would apply to the acceptance, processing, or approval of applications for development permits related to data centers, cryptocurrency mining facilities, and server farms within the Town’s planning and zoning jurisdictionFrom an official notice. Vote: Unanimous | Moratorium | In force | Feb. 11, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Chatham County * What it saysA temporary moratorium is hereby imposed commencing on February 11th, 2026, and expiring no later than February 11th, 2027, or on approval of new zoning regulation regarding data centers, data processing facilities, cryptocurrency mining operations, and uses associated with data processing facilities not yet defined in the Chatham County Zoning Ordinance.From the instrument | Moratorium | In force | Feb. 11, 2026 | Feb. 11, 2027 | 1 | Double-coded; two or more independent news sources Source ↗ |
| Mooresville town | Moratorium | In force | Nov. 2, 2026 | Not stated | 0 | Government record; single-coded Source ↗ |
| Beaufort County | Moratorium | In force | Oct. 5, 2026 | Oct. 5, 2027 | 0 | News report; single-coded Source ↗ |
| Statesville city | Moratorium | In force | Sept. 14, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Vance County | Moratorium | In force | Sept. 14, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Southport city | Moratorium | In force | Sept. 10, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Nash County | Moratorium | In force | Sept. 8, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Hendersonville city | Moratorium | In force | Sept. 3, 2026 | Sept. 3, 2027 | 0 | Tracker lead only; not counted in any headline |
| Lincolnton city | Moratorium | In force | Sept. 3, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| McDowell County | Moratorium | In force | Aug. 31, 2026 | Feb. 28, 2027 | 0 | News report; single-coded Source ↗ |
| Whiteville city | Moratorium | In force | Aug. 25, 2026 | Aug. 25, 2027 | 0 | News report; single-coded Source ↗ |
| Hildebran town | Moratorium | In force | Aug. 24, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Yadkin County | Moratorium | In force | Aug. 24, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Highlands town | Moratorium | In force | Aug. 20, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Warren County | Moratorium | In force | Aug. 19, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Greensboro city | Moratorium | In force | Aug. 18, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Alamance County | Moratorium | In force | Aug. 17, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Waxhaw town | Moratorium | In force | Aug. 11, 2026 | Aug. 11, 2027 | 0 | News report; single-coded Source ↗ |
| Nashville town | Moratorium | In force | Aug. 4, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Camden County | Moratorium | In force | Aug. 3, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Edgecombe County | Moratorium | In force | Aug. 3, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Farmville town | Moratorium | In force | Aug. 3, 2026 | Aug. 3, 2027 | 0 | News report; single-coded Source ↗ |
| Mount Airy city | Moratorium | End date passed; no outcome on record | July 16, 2026 | Sept. 14, 2026 | 0 | News report; single-coded Source ↗ |
| Hot Springs town | Moratorium | In force | July 13, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Davie County | Moratorium | In force | July 6, 2026 | July 6, 2027 | 0 | News report; single-coded Source ↗ |
| Franklin town | Moratorium | In force | July 6, 2026 | July 6, 2027 | 0 | News report; single-coded Source ↗ |
| Asheville city | Moratorium | In force | June 23, 2026 | June 23, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| Holly Springs town | Moratorium | In force | June 16, 2026 | June 16, 2027 | 0 | News report; single-coded Source ↗ |
| Cumberland County | Moratorium | In force | June 15, 2026 | Dec. 15, 2026 | 0 | News report; single-coded Source ↗ |
| Charlotte city | Moratorium | End date passed; no outcome on record | June 8, 2026 | Nov. 5, 2026 | 1 | Double-coded; not headline-eligible Source ↗ |
| Boiling Spring Lakes city | Moratorium | In force | June 2, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Surry County | Moratorium | In force | June 1, 2026 | July 20, 2028 | 0 | News report; single-coded Source ↗ |
| Whitakers town | Moratorium | In force | June 1, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Hillsborough town | Moratorium | In force | May 27, 2026 | May 27, 2027 | 0 | Tracker lead only; not counted in any headline |
| Wilson city | Moratorium | In force | May 21, 2026 | May 21, 2027 | 0 | Tracker lead only; not counted in any headline |
| Garner town | Moratorium | In force | May 19, 2026 | Not stated | 0 | Double-coded; not headline-eligible Source ↗ |
| Woodfin town | Moratorium | In force | May 19, 2026 | May 19, 2027 | 0 | News report; single-coded Source ↗ |
| Bailey town | Moratorium | In force | May 18, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Pasquotank County | Moratorium | In force | May 18, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Harnett County | Moratorium | In force | May 4, 2026 | May 4, 2027 | 0 | News report; single-coded Source ↗ |
| Northampton County | Moratorium | In force | May 4, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Spring Hope town | Moratorium | In force | May 4, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Swain County | Moratorium | In force | April 21, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Watauga County | Moratorium | In force | April 21, 2026 | April 21, 2027 | 0 | News report; single-coded Source ↗ |
| Rowan County | Moratorium | In force | April 20, 2026 | April 20, 2027 | 0 | News report; single-coded Source ↗ |
| Clyde town | Moratorium | In force | April 16, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Wendell town | Moratorium | In force | April 13, 2026 | Dec. 31, 2026 | 0 | Tracker lead only; not counted in any headline |
| Boone town | Moratorium | In force | March 23, 2026 | March 23, 2027 | 0 | News report; single-coded Source ↗ |
| Brevard city | Moratorium | In force | March 16, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Canton town | Moratorium | In force | Feb. 11, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Gates County | Moratorium | In force | Dec. 17, 2025 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Clay County | Ban | In force | Not stated | Not stated | 0 | Double-coded; not headline-eligible |
| Clay County | Moratorium | In force | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Elizabeth City city | Moratorium | In force | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Fayetteville city | Moratorium | In force | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| King city | Moratorium | In force | Not stated | Not stated | 0 | Government record; single-coded Source ↗ |
| Newport town | Moratorium | In force | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Columbus County * | Moratorium | Vote scheduled | Oct. 5, 2026 | On a condition | 0 | Double-coded; not headline-eligible Source ↗ |
| Avery County | Moratorium | Proposed | Not stated | Not stated | 0 | Government record; single-coded Source ↗ |
| Davidson County | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Elizabethtown town | Moratorium | Vote scheduled | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Guilford County | Moratorium | Vote scheduled | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Halifax County | Moratorium | Vote scheduled | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Pitt County | Moratorium | Vote scheduled | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Mayodan town | Moratorium | Replaced by permanent rules | May 11, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Cherokee County | Moratorium | Expired | Oct. 2, 2023 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Madison County | Moratorium | Expired | June 13, 2023 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Forsyth County | Moratorium | Rejected | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Stokes County | Moratorium | Rejected | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
* The ordinance has a conditional sunset trigger (for example, “remains in effect until permanent industrial zoning standards are adopted”); hover the asterisk for the ordinance text.
North Carolina entitlement FAQ
How many active data center moratoriums are currently in force across North Carolina?
As of Nov. 18, 2026, North Carolina has 66 data center moratoriums or bans on record as in force, including 10 double-coded and confirmed by a government record, an official notice or two independent news outlets. 7 more are proposed or scheduled for a council vote, and 3 earlier pauses have expired or been replaced by permanent zoning rules; 2 proposals were rejected. The list may be incomplete; nationally, a blind search found 83.7% of instruments already in the register.
Which planned North Carolina data center campuses are affected by local permitting freezes?
2 of the in-force instruments have at least one planned data center project inside the boundary (county-wide reading). Projects under construction or operating aren't affected: they already hold their approvals. Whether a planned project is covered depends on the approvals it already holds and on the instrument's own scope; the table quotes the text where we have it.
For national benchmarks, source-tier definitions and statistical methodology, see the Moraine US Data Center Moratorium Register.