Colorado data center moratoriums & entitlement directory
As of Nov. 18, 2026, Colorado has 30 data center moratoriums or bans on record as in force, including 4 double-coded and confirmed by a government record, an official notice or two independent news outlets. 6 more are proposed or scheduled for a council vote, and 0 earlier pauses have expired or been replaced by permanent zoning rules; 1 proposal was rejected. Nationally, 76% (56 of 74) of data center moratoriums that reached their initial sunset date with a recorded outcome were extended. Treat every stated expiration date below as the earliest possible catalyst window, never as a guaranteed reopening date.
- in force
- 30
- double-coded and confirmed
- 4
- proposed or vote scheduled
- 6
- in force with a planned project inside
- 0
Geographic map: in-force and pending Colorado restrictions
- Dark red: in-force restriction on a government record or in the press.
- Light red: in-force restriction reported on industry tracker lists, pending primary-source confirmation.
- Yellow: ordinance formally proposed or scheduled for a council vote.
Hover over any county or municipality for its current legal status; click for enactment and sunset dates, vote tally, ordinance text and source, where on file.
Upcoming catalyst calendar (next 90 days)
Boulder County · Stated expiry · Source
Complete Colorado instrument ledger (37 tracked actions)
Sorted by legal status (in force, pending, concluded). Each record displays its verification tier, including 13 in-force rows resting on unconfirmed tracker leads, published so they can be checked in diligence. Legislative status is never inferred: “Not stated” means no primary document or press report we found gives a sunset date.
| Jurisdiction | Type | Status | Enacted | Ends | Pipeline campuses inside | Source |
|---|---|---|---|---|---|---|
Thornton city What it saysAn ordinance establishing a temporary moratorium on the submission, acceptance, processing, or approval of any applications to the City of Thornton for any permit, license, plan approval, or other type of approval related to new or expanding of data centers.From an official notice. Vote: 5-4 | Moratorium | In force | Sept. 22, 2026 | Not stated | 0 | Double-coded; official notice Source ↗ |
Broomfield city * What it saysshall not accept applications or engage in pre-submittal activities for data center facilities, as defined in this ordinance ... for the period of eighteen (18) months from the effective date of this ordinanceFrom the instrument | Moratorium | In force | July 7, 2026 | Jan. 19, 2028 | 0 | Double-coded; government record Source ↗ |
Montrose County What it saysThe Montrose County Board of Commissioners unanimously approved a six-month moratorium on new data center facility applications in Montrose CountyFrom a news report. Vote: Unanimous | Moratorium | In force | July 1, 2026 | Not stated | 0 | Double-coded; two or more independent news sources Source ↗ |
Boulder County * What it saysPlanning applications for data centers and detention centers will not be accepted for unincorporated Boulder County after the Boulder County Commissioners unanimously passed a temporary moratorium. ... This means that applications relating to data centers and detention centers will not be considered while the Code is being reviewed.From an official notice. Vote: Unanimous | Moratorium | In force | June 2, 2026 | Dec. 2, 2026 | 0 | Double-coded; official notice Source ↗ |
| Mesa County | Moratorium | In force | Sept. 30, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Loveland city | Moratorium | In force | Sept. 15, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Mead town | Moratorium | In force | Aug. 31, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Fremont County | Moratorium | In force | Aug. 25, 2026 | Feb. 23, 2027 | 0 | News report; single-coded Source ↗ |
| Cedaredge town | Moratorium | In force | Aug. 20, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Paonia town | Moratorium | In force | Aug. 11, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Rio Grande County | Moratorium | In force | Aug. 5, 2026 | Aug. 5, 2027 | 0 | News report; single-coded Source ↗ |
| Milliken town | Moratorium | In force | July 30, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Lochbuie town | Moratorium | In force | July 21, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Johnstown town | Moratorium | In force | July 20, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Monument town | Moratorium | In force | July 20, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Woodland Park city | Moratorium | In force | July 16, 2026 | Jan. 16, 2028 | 0 | Tracker lead only; not counted in any headline |
| Delta County | Moratorium | In force | July 7, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Hudson town | Moratorium | In force | July 1, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| South Fork town | Moratorium | In force | June 18, 2026 | Not stated | 0 | News report; single-coded Source ↗ |
| Archuleta County | Moratorium | In force | June 16, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Buena Vista town | Moratorium | In force | June 9, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Grand County | Moratorium | In force | June 9, 2026 | June 24, 2027 | 0 | Tracker lead only; not counted in any headline |
| Jefferson County | Moratorium | In force | May 19, 2026 | March 19, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| Denver city | Moratorium | In force | May 18, 2026 | May 21, 2027 | 0 | Double-coded; not headline-eligible Source ↗ |
| Saguache County | Moratorium | End date passed; no outcome on record | May 5, 2026 | Nov. 5, 2026 | 0 | News report; single-coded Source ↗ |
| Phillips County | Moratorium | In force (extended) | Feb. 27, 2026 | Not stated | 0 | Tracker lead only; not counted in any headline |
| Larimer County | Moratorium | In force (extended) | Jan. 27, 2026 | Feb. 25, 2027 | 0 | Government record; single-coded Source ↗ |
| Fort Collins city | Moratorium | In force | Not stated | April 6, 2027 | 0 | Government record; single-coded Source ↗ |
| Grand Junction city | Moratorium | In force | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Kiowa County | Moratorium | In force (extended) | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Logan County | Moratorium | Proposed | Oct. 21, 2025 | Not stated | 0 | News report; single-coded Source ↗ |
| Arvada city | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Brighton city | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Commerce City city | Moratorium | Vote scheduled | Not stated | Not stated | 0 | Tracker lead only; not counted in any headline |
| Moffat County | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Pagosa Springs town | Moratorium | Proposed | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
| Aurora city | Moratorium | Rejected | Not stated | Not stated | 0 | News report; single-coded Source ↗ |
* The ordinance has a conditional sunset trigger (for example, “remains in effect until permanent industrial zoning standards are adopted”); hover the asterisk for the ordinance text.
Colorado entitlement FAQ
How many active data center moratoriums are currently in force across Colorado?
As of Nov. 18, 2026, Colorado has 30 data center moratoriums or bans on record as in force, including 4 double-coded and confirmed by a government record, an official notice or two independent news outlets. 6 more are proposed or scheduled for a council vote, and 0 earlier pauses have expired or been replaced by permanent zoning rules; 1 proposal was rejected. The list may be incomplete; nationally, a blind search found 83.7% of instruments already in the register.
Which planned Colorado data center campuses are affected by local permitting freezes?
None of the in-force instruments in Colorado has a planned data center project inside its boundary on Moraine's map. Projects under construction or operating aren't affected: they already hold their approvals.
For national benchmarks, source-tier definitions and statistical methodology, see the Moraine US Data Center Moratorium Register.